Speed is one of the reasons many families choose steel framing. But how long does it really take? We reviewed the dates of our latest turnkey projects to give you realistic timelines.
Timelines by home size
Counting from pouring the concrete slab to the finished home: homes up to 100 m², 5 to 9 months; homes of 140 to 220 m², 7 to 10 months.
Before construction there is the design, documentation and permits stage, which took 1 to 4 months on our projects.
The construction stages
1. Foundations: under-slab drainage and concrete slab. 2. Structure: galvanized steel framing and OSB bracing. 3. Envelope: roof, membrane, EIFS insulation and exterior render. 4. Installations: water, gas and electricity inside the walls. 5. Interior: glass wool, drywall, joint finishing and paint. 6. Finishes: windows and doors, flooring, tiles, kitchen and bathrooms.
Why it is faster than traditional construction
It is dry construction: apart from the slab, there is no waiting for masonry and plaster to cure or dry. The structure and enclosures progress alongside the installations, and materials are bought in advance.
What can extend the timeline
Pending decisions: choosing windows, flooring, tiles and fixtures on time keeps the build moving. Changes and extras during construction. Rain during the slab stage. Loan disbursements, if the project is bank-financed. Size and second stories: the larger and more complex, the longer it takes.
In the in-person meeting we give you an estimated schedule for your project.